Kohima–Jessami road: HC seeks contractor’s assurance on March 2027 deadline

HC seeks contractor’s assurance on March 2027 deadline

HC seeks contractor’s assurance on March 2027 deadline

Morung Express News
Dimapur | November 18

The Gauhati High Court Kohima Bench has directed the contractor executing Package-II of the Kohima–Jessami Road to explain the steps taken to deploy adequate machinery and manpower and state whether it can complete the project by March 1, 2027, amid concerns over slow progress.

A Division Bench of Justice Robin Phukan and Justice Yarenjungla Longkumer passed the order on November 18 while hearing a public interest litigation filed by the Chakhesang Public Organisation and another petitioner.

The Court was informed through affidavits filed by the Authority Engineer and the National Highways and Infrastructure Development Corporation Limited (NHIDCL) that the project had achieved only 46.98% physical progress and 45.55% financial progress as of October 2026.

According to the Authority Engineer’s affidavit, the first contractor had achieved 58.08% physical progress and 54.08% financial progress before its contract was terminated. The balance work was subsequently awarded to Ratna Infrastructure Projects Pvt Ltd through a letter of award dated October 10, 2023.

The affidavit stated that the contractor had been repeatedly directed to mobilise adequate plant, machinery, equipment and manpower. However, progress remained slow, with only around 4.70% physical progress achieved between the appointed date and January 2025, a period of approximately one year.

The contractor was granted an extension of time up to March 1, 2027, through a letter dated September 18, 2026. However, the Authority Engineer informed the Court that progress during the preceding month was less than 2%.

NHIDCL also submitted that several notices had been issued to the contractor over its failure to maintain the required rate of progress in accordance with the approved construction programme and contractual milestones. It also flagged inadequate mobilisation of resources at the project site.

The Court has allowed the contractor to file its reply to both affidavits by November 25. The reply must specify the steps taken to deploy sufficient machinery and manpower and categorically state whether the contractor can complete the project by the revised deadline.

The matter has been listed for further hearing on November 25, with the Authority Engineer directed to remain personally present.

The case concerns the 21.90-km Chakhabama–Kikrüma stretch of NH-29, which forms Package-II of the Kohima–Jessami Road. The contract was awarded to Ratna Infrastructure Projects in October 2023, with the appointed date of January 5, 2024, and an original completion period of 24 months. In an earlier order on September 30, the High Court had described the progress as “not satisfactory” and sought a comprehensive report on the reasons for the delay.
 