1. Dimapur – Kohima – Mao:
(a) Km 174.90 KachhraNala – Sinking is continuous and the road is closed. Alternate road of Jotsoma bypass is available for all traffic. (b) Kohima – Mao – The road from Kohima to Mao is reported as okay.
2. Kohima – Jessami:
(a) Km 37 – Formation is damaged and slides are continuing. Works will commence once the slides stop, will take 10-15 days depending on ground conditions. Equipments are available. (b) Mesulomi Bridge – Reported okay for all vehicles.
3. Tuensang - Mon:
(a) Km 23 – Culvert and formation is washed off. Works commenced from Tuensang side and will take 10-15 days for restoration due to heavy flow in the river. (b) There are numerous slides between Hakchang and Tobu and fresh slide between Km 66 - Km 67, which will be cleared within 1-2 days. There was a cloudburst between Km 66 – Km 67 and fresh slides are still occurring. (c) Road from Mon to Hakchang will be opened in a day or two. Similarly, road from Tuensang to Km 23 will also be opened in a few days time.
(DIPR)