Nagaland Govt proposes Integrated Zonal Waste Processing Centre at Xukiye
• Submission to NGT indicates move comes amid Dobagaon site stall
• Proposed centre to serve Dimapur, Chümoukedima and Niuland areas
Moa Jamir
Dimapur | August 25
The Nagaland Government has informed the National Green Tribunal (NGT) that it has decided to acquire fresh land at Xukiye village under Niuland district for an Integrated Zonal Waste Processing Centre.
The move follows the failure to operationalise an earlier waste management site at Dobagaon due to opposition and concerns over its conformity with the Solid Waste Management Rules, 2016, according to an additional compliance report filed on August 5 in the Sunrise Colony dumping area matter.
The Government stated that it had earlier acquired 10.74 acres of land at Dobagaon for setting up a waste management site/landfill for the Dimapur Municipal Council (DMC). Although DMC took possession of the land in May 2026, no waste management activity could be initiated due to “fierce opposition and non-cooperation” from citizens of Dobagaon and surrounding villages.
The villagers alleged departmental misinformation to village authorities regarding activities proposed at the site during the land purchase negotiation process. The report also stated that the site did not meet certain criteria under the Solid Waste Management Rules, 2016, particularly due to severe erosion by the Dhansiri River.
Accordingly, the State Government decided to acquire a fresh 50 acres of land at Xukiye for the Integrated Zonal Waste Processing Centre.
The proposed centre is intended to cater to DMC, East Dimapur Town Council, Chümoukedima Town Council, Niuland Town Council, Rural Local Bodies and peripheral settlements across Dimapur, Chümoukedima and Niuland districts.
Approval to initiate land acquisition was conveyed to the Commissioner and Director of Land Revenue on July 27, 2026, the submission stated. The site was expected to become operational within eight months, with a corresponding time extension sought for compliance.
Other compliance status
Meanwhile, the August 5 submission listed several works reported as completed at the existing Sunrise Colony dumpsite, including the creation of a green belt and buffer zone in May 2024 and construction of linear drainage inside the dumpsite periphery in July 2026.
It also reported that complete fencing of the site, including additional fencing towards the Dhansiri River, was completed on or about June 2, 2026. Six CCTV cameras were installed and commissioned on August 7, 2025.
Bio-remediation at the site was ongoing at a rate of 60 to 100 metric tonnes per day, while bio-mining was stated to be 80% complete, with the entire process expected to be completed within two years.
Several works, however, remained pending, including installation of a weighbridge, construction of a concrete slab for waste processing and segregation, and an Effluent Treatment Plant.
The submission further stated that work on a 150 KLD Fecal Sludge Treatment Plant at Shozukhu was 70% complete, while waste segregation had been implemented in some DMC wards and was proposed to be extended to the remaining urban local bodies.
NGT says order remains unfulfilled
Two days after the compliance report was filed, the NGT Eastern Zone Bench, Kolkata, on August 7 recorded the filing of the additional compliance affidavit and report and observed that its February 3, 2023 order was “yet to be fully complied with.”
The Tribunal expressed “strong displeasure” over the failure of the concerned authorities to give due attention and priority to its directions, noting that more than three years had elapsed without due compliance. It cautioned that heavy costs could be imposed on the concerned officers and authorities if the orders continued to remain unexecuted.
The NGT, however, granted the Chief Secretary, Government of Nagaland, and the Municipal Commissioner, DMC, one more opportunity to file additional compliance affidavits with specific undertakings on the remaining works and the dates by which they would be completed.
The matter stems from an application before the NGT concerning solid waste management and the handling of the existing dumpsite at Sunrise Colony, Dimapur. In its February 3, 2023 order, the Tribunal had issued a series of time-bound directions to the State authorities and DMC.
The next hearing of the matter is listed on October 14, 2026.
Compliance status as reported
February 3, 2023: The National Green Tribunal issued time-bound directions covering alternative land for a dumpsite, waste segregation, bio-remediation, green belt and buffer zone, weighbridge, waste processing infrastructure, drainage, ETP, FSTP, bio-mining, fencing and CCTV surveillance. | |
Directive | Status reported |
Alternative land for new dumpsite - Compliance was to be made within 31.01.2024 | 10.74 acres acquired at Dobagaon but could not be operationalised due to opposition and site concerns. Fresh 50 acres proposed at Xukiye; site expected to be operational within eight months. |
Waste Management Action Plan - Compliance was to be made within 30.04.2023. | Prepared and submitted to the Government in March 2023; reported as complied. |
Waste segregation at source - Within one month from the date of order i.e. 3rd February, 2023 | Implemented in some DMC wards; proposed for remaining ULBs within three months. |
Bio-remediation -To be completed by 31.05.2024 | Ongoing at 60–100 metric ton per day. |
Green belt and buffer zone - To be completed by 30.09.2023 | Reported completed in May 2024. |
Weighbridge -To be completed by 31.05.2023 | Not yet complied - likely to be complied within six months henceforth and/or six months from the operation and functioning of the Ring-Fence Account opened under the direction of NGT Principal Bench. |
Concrete slab for waste processing -To be completed by 31.05.2023 | Not yet complied - likely to be complied within six months henceforth and/or six months from the operation and functioning of the Ring-Fence Account opened under the direction of NGT Principal Bench. |
Linear drainage -To be completed by 31.05.2023 | Reported completed in July 2026. |
Effluent Treatment Plant - To be completed by 31.05.2024 | Not yet complied; -Work for 150 KLD FSTP in progress with 70% completion in Shozukhu for Dimapur and adjoining areas. Work order issued on 13th November, 2024. |
Construction of Fecal Sludge Treatment Plant (FSTP) with higher capacity - To be completed by 31.05.2024 | Not yet complied; -Work for 150 KLD FSTP in progress with 70% completion in Shozukhu for Dimapur and adjoining areas. Work order issued on 13th November, 2024. Expected to be within five months. |
Bio-mining -- To be completed by 31.05.2024 | 80% complete; expected to be completed within two years. |
Complete fencing of dumping site | Reported completed on or about June 2, 2026. |
Installation of CCTV cameras for monitoring | Installed; commissioned on August 7, 2025. |
Compliance Committee | Notified on August 3, 2026. |
Quarterly review | To commence following constitution of the Committee. |
Source: Submission by the Nagaland State respondents to NGT on August 5. | |
The article is updated to reflect a factual correction.