Kohima–Jessami Road PIL: HC orders independent site inspection

Morung Express News
Dimapur | November 29

The Gauhati High Court’s Kohima Bench has constituted a two-member committee to independently inspect the delayed Chakhabama–Kikrüma stretch of the Kohima–Jessami road (Package-II), after the executing contractor attributed slow progress to pending approval of Change of Scope (COS) proposals worth Rs 36.49 crore.

A division bench comprising Justice Robin Phukan and Justice Yarenjungla Longkumer passed the order on November 25 while hearing public interest litigation (PIL) filed by the Chakhesang Public Organisation and another petitioner against the Union of India, NHIDCL, the State Government and others.

In an additional affidavit, M/s Ratna Infrastructure Projects Pvt Ltd stated that the Authority’s Engineer had recommended three COS components covering the Chakhabama Military Area, exposed and damaged pavement surfaces, and treatment of sinking locations, including four sinking zones.

The proposed changes involve an additional Rs 36,49,15,116.10, approximately 52.88% above the original contract price of Rs 69 crore, it said.  The recommendations had not been approved by NHIDCL as of November 25.

The contractor contended that the lack of approval had left it without adequate work fronts to execute the remaining works, although it had completed 100% of the work in undisputed areas. It stated that it would submit a construction programme within seven days of receiving final approval on the scope of work but could not commit to a completion schedule in the absence of clarity.

The Authority’s Engineer, present in court, did not deny the averments concerning the COS proposals.

The Court accordingly constituted a two-member committee comprising Advocate Joshua Sheqi as Convenor and a senior engineer with experience in highway construction, not below the rank of Executive Engineer, to be nominated by the Chief Engineer, PWD (Highways), Government of Nagaland, within seven days of receipt of the order. The nominated engineer must have had no involvement in the execution or supervision of the project.

The committee has been directed to undertake a physical inspection of the entire road stretch and assess the actual chainage-wise progress of construction, adequacy of machinery, manpower and other resources deployed, reasons for delays and impediments to execution, the necessity of the three proposed COS components, and the feasibility of completing the remaining work within the stipulated timeline. It must submit a report, duly signed by both members and accompanied by photographs, before the next date of listing.

The Court also directed NHIDCL to file an affidavit responding to the contractor's contentions and provide the committee with relevant project records, including the DPR, contract agreement, progress reports and quality control records.

NHIDCL has been directed to bear the committee's inspection and incidental expenses. Its counsel and Executive Director (Projects), NHIDCL Kohima, have also been directed to remain present at the next hearing, along with the Authority’s Engineer. The matter has been listed for further orders on February 10, 2027.
 